logo

Construction

Here you'll find the latest updates on the work taking place on Church Road. If you have a question on the work please email us.

Updated on 29.07.16

Blended 'Copenhagen' crossings have been installed at the following locations:

  • Crescent Road
  • Farm Road
  • Simonds Road
  • Tallack Road
  • Villiers Close
  • Palamos Road
  • Malta Road
  • Wiseman Road
  • Marconi Road
  • Rosedene Crescent
  • Goldsmith Road
  • Gloucester Road
  • Marsh Lane
  • Capworth Street.

Raised tables - which involve raising the road to pavement level to slow down vehicles - have been installed at the following locations:

  • Capworth Street
  • Park Road/ Marsh Lane
  • Rosedene Crescent/ Goldsmith Road.

A new pedestrian and cycle crossing has been installed on Leyton Grange Road.

A new protected cycle track has been installed between Gloucester Road and Capworth Street.

 

Updated on 12.04.16

Work is still underway on the following:

  • At the new pedestrian and cycle crossing at Leyton Grange Road
  • Upgrading and relocating the lamp columns along the route
  • Upgrading the two floating bus stops.

The following work will begin between 4 and 18 April:

  • New blended 'Copenhagen' crossings at Gloucester Road
  • New blended 'Copenhagen' crossings at Rosedene Terrace
  • Raising the road to pavement level at Gloucester Road/ Rosedene Terrace to create a 'raised table'
  • Creating the new protected cycle track between Gloucester Road and Capworth Street
  • Installing a new crossing at Leyton Grange Road
  • Installing new shelters at the two new floating bus stops.

Updated 01.04.16

  • 20160229_140541_resizedDue to the Easter/ Bank Holiday and the increased likelihood of pedestrian footfall along the route, no new large excavations will be dug and left open
  • The following work has been completed:
    • Drainage and duct work for the new signal crossing at Leyton Grange
    • Blended crossing at Crescent Road
    • Blended crossing at Ive Farm Close
    • Blended crossing at Simonds Road
    • Blended crossing at Tallack Road
    • Blended crossing at Villiers Close
    • Blended crossing at Palamos Road
    • Blended crossing at Malta Road
    • Blended crossing at Wiseman Road
    • Road resurfacing
  • Work is continuing on the new pedestrian and cycle crossing at Leyton Grange Road
  • Work is continuing on upgrading the two floating bus stops
  • Throughout April work will take place on the following:
    • Blended crossing at Gloucester Road
    • Blended crossing at Rosedene Road
    • The protected cycle track between Gloucester Road and Capworth St.

Updated 08.02.16

  • New blended 'Copenhagen' crossings have been completed at the following side road junctions on Church Road
    • Crescent Road
    • Tallack Road
    • Simonds Road
    • Rosedene Terrace.
  • We're currently upgrading the two bus stops closest to the Marsh Lane crossing, highering the kerb to make them suitable for wheelchair and pushchair access
  • Work has started between Villers Close and Ive Farm on the new protected cycle lane and footway
  • A new blended 'Copenhagen' crossing is being constructed on Wiseman Road
  • Work on the new blended 'Copenhagen' crossings will take place over the next two weeks on the following roads:
    • Marconi Road
    • Palamos Road
    • Villiers Close
  • Advanced Notice - Church Road will be closed to through traffic overnight for five nights for road resurfacing. During this time there will be restricted access to side roads between Marsh Lane and Oliver Road.

Updated 01.02.16

  • A new blended Copenhagen crossing has been created at the junction of Crescent Road
  • Work is continuing between Villers Close and Ive Farm and soon work will begin on constructing the new protected cycle lane and crossing
  • Blended Copenhagen crossing are being created on Simmonds Road and Tallack Road.

Updated 18.01.16

  • On 11 January 2016 work began on the new signal crossing at Leyton Grange
  • On 18 January 2016 work began between Villers and Ive Farm.

 

BACK TO CHURCH ROAD>>